Projects

Santa Nella Rehab

July 19, 2018

Myers and Sons Construction won this project through Caltrans as a prime contractor. It was bid at $3.3 million with 120 working days. The scope of work included placing and furnishing 146,514 square-feet of polyester concrete overlay, 1,879 linear feet of joint seal replacement of various sizes and Type R structural approach slab work.